Public Works Project Updates

Information on current Town of Vienna public works projects can be found below, including contact information for the project manager assigned to each project.

Main improvement includes bumping out the curb ramps located at the Ayr Hill Avenue leg of the Ayr Hill Avenue and Lawyers Road intersection.  This improvement may also include adding some curb and gutter along Ayr Hill Avenue near the intersection, replacing/adding sidewalk, adding driveway aprons, and on-street parking lines where applicable.  This will create a narrowing of Ayr Hill Avenue within the area of the intersection and also create a safer environment for pedestrians.

Project Details:

Project Manager:  Andrew Jinks, PE
Project Status:  Under Design
Anticipated Construction Start Date:  Spring/Summer 2026

 Fall 2024  Design Begin
Spring 2025  60% Design
 Winter 2025  100% Design Complete
 Spring/Summer 2026  Construction Begins
 Fall 2026  Construction Complete

This project will restore approximately 1,900 linear feet of natural stream and stabilize the steep, eroded stream banks along Bear Branch from Cottage Street SW downstream to I-66.  This stretch of stream runs parallel to Patrick Street SW and George C. Yeonas Park.  The completed project will reduce sedimentation and improve the stream's water quality using natural channel design techniques.

Project Details

Project Budget:  $2,040,000
Project Manager:  Alan Chen, PE
Anticipated Construction Date: September 2024

Bear Branch SLAF Application Package(PDF, 545KB)

Status Summary and Tentative Schedule

Oct. 10, 2018  Stream restoration grant application submitted
Aug. 19, 2019  Town Council approves design funding agreement with Fairfax County
July 17, 2020  Begin survey
Dec. 15, 2020  Community meeting on concept plan design
Sept. 8, 2022  Community meeting on 90% design plan
March 2024  100% design completed 
Aug. 26, 2024  Town Council to approve construction contract for Bear Branch Stream Restoration 
April 2025  Construction begins for Bear Branch Stream Restoration
Sept. 2025  Construction anticipated to be completed. 

This project will restore approximately 2,300 linear feet of natural stream and stabilize the steep, eroded stream banks along Bear Branch Tributary from Cottage Street, SW downstream to I-66.  This stretch of stream runs parallel to Walker Street, SW.  The completed project will reduce sedimentation and improve the stream's water quality using natural channel design techniques.

Project Details

Project Budget:  $2,520,000
Project Manager:  Alan Chen, PE
Anticipated Construction Date:  TBD

Bear Branch Tributary Phase II - SLAF Application Package(PDF, 6MB)

Status Summary and Tentative Schedule

January 2022

Town Council approves design funding agreement with Fairfax County

Aug. 29, 2022

Town Council awards the engineering design contract

November 2022

Survey crews scheduled to be on site over a period of about six weeks

November 2025

100% construction design to be completed

 Spring 2026

Anticipated construction start date

This project will provide a new curb, gutter, and sidewalk on both sides of Church Street NE between Park Street and Glyndon Street and both sides of Glyndon Street from Maple Avenue to Ayr Hill Avenue. A separate roadway and drainage project on Glyndon Street from Ayr Hill Avenue to Jean Place will connect to this project.

638828090969800000.jpg

 

Project Budget:  $600,000

Contact:  DPW@viennava.gov

Anticipated Construction Date:  2025

Link to Concept Plan - July 2025(PDF, 14MB)

 

Status Summary and Tentative Schedule

April 14, 2021 Approval of Project Funding (NVTA Funds)
August 13, 2025 Public Meeting to Present Design
Early 2026 Town Council Approval of Construction Contract
2026 Construction Start

 

 

 

This project's purpose is to rebuild existing sidewalks to conform to current ADA standards and construct missing sections to provide a safe, accessible pedestrian route on Creek Crossing Road from Beulah Road, NE, to Old Courthouse Road. This is a cooperative project with the Fairfax County Department of Transportation.

Project Details

Project design budget: $400,000

Project Manager: Andrew Jinks, PE

Video of Dec. 2, 2020 Customer Information Meeting

Fairfax County Creek Crossing Proposed Design Map(PDF, 2MB)

Vienna Creek Crossing Proposed Design Map (updated: May 2022)(PDF, 3MB)

Dec. 2, 2020 Creek Crossing Citizen Meeting Transcript (comments and responses)(PDF, 2MB)

Status Summary and Tentative Schedule

*contingent upon obtaining funding for construction

Dec. 2, 2020 Citizens Information Meeting
Dec. 16, 2020 Citizen comment period closes
August 2022 Submit 60% Plans
Spring 2026* Start R/W negotiations
Spring 2028  Anticipated start of construction.

This project will provide sidewalk on one side of Glen Avenue, SW, from Courthouse Road, SW, to just before Liberty Lane, SW, (tying into the existing sidewalk built by the Sunrise development).  The improvements also include curb and gutter along Glen Avenue, SW, and drainage improvements typically seen with new sidewalk projects.  Funding for the project is from the American Rescue Plan Act (ARPA).

Project Details 

638756419098900000.jpg

Project design budget:  $145,000
Project Manager:  Andrew Jinks, PE
Anticipated Construction Date:  Spring 2025

March 20 Glen Avenue, SW Sidewalk CIM Design Exhibits(PDF, 17MB)

Glen Avenue, SW Sidewalk - Option C May 2024 (option moving forward)(PDF, 3MB)

Glen Avenue, SW Sidewalk - 95% Plans(PDF, 25MB)

 

Status Summary and Tentative Schedule

Spring 2023  Town Council approves design contract
March 20, 2024 Community Information Meeting (CIM)
Nov. 18, 2024 Town Council approval of funding
Fall 2025 Anticipated construction start date

The 300 block of Glyndon Street, NE, is an existing "shoulder and ditch" roadway with minimal drainage infrastructure.  In heavy rains, stormwater flows across the street and floods private property on the west side.  Work on the project was paused until additional funding was available.  In 2024, the American Rescue Plan Act (ARPA) provided the necessary funds to complete the design and fund the construction.  This project includes curb and gutter on both sides of the roadway and sidewalk on the south side of the roadway from Ayr Hill Avenue to Jean Place.  Note:  work in front of the Glyndon Park parking lot is not included with this project.  Modifications to the parking lot, if any, will be made by Parks and Recreation.  New storm drain pipes and inlets will be constructed within the project limits.  

A separate project, Church Street, NE, Sidewalk Improvement Project, includes construction of curb, gutter and sidewalk on Glyndon Street from Ayr Hill Avenue to Maple Avenue.

Project Details 

638828090969800000.jpg

Project budget:  $1,800,000

Contact:  DPW@viennava.gov

Anticipated construction date:  Spring 2025

Glyndon Street NE link to Plans(PDF, 35MB)

 

 

 

 

 

 

 

Status Summary and Tentative Schedule

Nov. 16, 2015 Engineering services contract awarded
June 22, 2016 Drainage study received
 July 20, 2016 Citizens exhibit received
 Feb. 21, 2018 30% engineering plans received
 Oct. 10, 2018 60% engineering plans received
 2023 - 2024 Allocation of ARPA Funding to project
Apil 23, 2024 Final engineering plans complete
Nov. 18, 2024 Town Council approves construction contract
Sprint 2025 Construction begins

In September 2010, following a public hearing, Town Council authorized application to the Virginia Department of Transportation (VDOT) for a Congestion Mitigation and Air Quality (CMAQ) grant to complete sidewalks on all streets within a one-mile radius of the Vienna Metro Station.  This is a federal grant that assists in completing projects that are regionally significant and provide transportation options to facilitate the use of mass transit.

This project completes all missing sections of sidewalk along Kingsley Road, SW, from Nutley Street to DeSale Street, SW.

Project Details

Project Budget:  TBD

Project Manager:  Andrew Jinks, PE

Anticipated construction date:  Not scheduled at this time

Status Summary and Tentative Schedule

September 2010  Town Council approves application for a VDOT CMAQ grant
 April 9, 2012  Proposal for engineering services received
May 7, 2012   Town Council awards design contract to Rinker Design Associates
 Dec. 15, 2014  Town Council consideration of CMAQ construction grant
 December 2016  On hold pending future funding
 October 2022  Restart design
 Summer 2024  Begin right-of-way negotiations
 Fall 2025  Advertise project for construction
 Spring 2026  Anticipated construction start date

In September 2010, following a public hearing, Town Council authorized application to the Virginia Department of Transportation (VDOT) for a Congestion Mitigation and Air Quality (CMAQ) grant to complete sidewalks on all streets within a one-mile radius of the Vienna Metro Station.  This is a federal grant that assists in completing projects that are regionally significant and provide transportation options to facilitate the use of mass transit.

This project completes all missing sections of sidewalk along Kingsley Road, SW, from Nutley Street to DeSale Street, SW.

Project Details

Project Budget:  TBD

Project Manager:  Andrew Jinks, PE

Anticipated construction date:  Not scheduled at this time

Status Summary and Tentative Schedule

September 2010 Town Council approves application for a VDOT CMAQ grant
April 9, 2012 Proposal for engineering services received
May 7, 2012  Town Council awards design contract to Rinker Design Associates
Dec. 15, 2014 Town Council consideration of CMAQ construction grant
December 2016 On hold pending future funding
October 2022 Restart design
Summer 2024 Begin right-of-way negotiations
Summer 2025 Complete coordination of pole relocation with Dominion Energy
October 2025 Anticipated start of construction

This project will install stockpile canopy covers for the stored materials at the Northside Property Yard to minimize the amount of contaminated stormwater runoff into the adjacent Piney Branch stream.

 Project Details

Project Budget: $250,000

Project Manager: Alan Chen, PE

Anticipated Construction Date: October 2024

Status Summary and Tentative Schedule

Aug. 26, 2024  Town Council Meeting for Approval of Construction Contract
Aug. 15, 2024 Board of Architectural Review Meeting Presentation
Aug. 8, 2024 Open Community Meeting at Mill St NE 
March 2024 Preliminary site survey completed
April 2024 Proposal and cost estimate received
August 2025 Installation of bin blocks and canopy cover to be completed

This project replaces the culvert under Nutley Street, SW, between Kingsley and Marshall roads, SW.

Project Details

Project Budget:  $500,000

Project Manager:  Alan Chen, PE

Anticipated Construction Date:  TBD

Nutley Street SW Culvert Plans(PDF, 19MB)

Status Summary and Tentative Schedule

June 2012 Town Council approves contract for drainage study
March 21, 2013 On-site citizen meeting
Nov. 18, 2013 Town Council awards final design contract
July 10, 2014 60% plans received 
Nov. 20, 2014 On-site citizen meeting
May 8, 2015 Design reviewed by VDOT
Aug. 21, 2015  On-site citizen final plan review
March 7, 2016 Town Council approves funds for additional hydraulic analysis
March 2017 Pending future CIP funding
June 2024 Design restarted with anticipated start of construction late in 2024
October 2024 100% Design completed and Town Council meeting scheduled for funding
December 2024 Construction contract awarded and initial site preparation to begin. 
Summer 2025 Construction to begin upon receipt of pending VDOT permit approval.

The existing asphalt path along the east side of Park Street, SE, (from the W&OD Trail to Fardale Street) is too narrow in many locations, the surface is uneven and is a frequent maintenance issue.  This project will replace the existing asphalt path with an ADA-compliant concrete sidewalk.  There are several segments of concrete sidewalk within these limits where the existing concrete sidewalk will be preserved.  The total length of asphalt trail to be replaced with concrete sidewalk is approximately 3500 feet.

Project Details

Project Budget:

Project Manager: Alsinia Ervin

Anticipated Construction Date:  2025

Park Street SE Link to Plans(PDF, 46MB)

Project Added to CIP September 19, 2022
Town Council Authorization to use ARPA Funding May 1, 2023
Town Council Approval of Design Contract June 5, 2023
Town Council Approval of Construction Funding Oct. 28, 2024

Improvements will consist of a new water meter installation, repairs to aging infrastructure, and provisions to increase functionality of the Town's water system.

Project Details

Project Construction Budget:  $2,500,000

Project Manager:  frank.torre@viennava.gov

Status Summary and Tentative Schedule

July 2023 Dogwood Street SW - between Cottage St. & Center St.  - COMPLETE
August 2023 Pruitt Court SW - Ware Street to cul-de-sac - COMPLETE
August 2023 Old Courthouse Road Check Valve and Vault - COMPLETE
October 2023 Hillcrest Drive SW between Tapawingo Rd.  & Kingsley Rd. - COMPLETE
December 2023 Polly Street SE between Wolftrap Dr. & Kramer Dr. - COMPLETE
January 2024 Wolftrap Road Insertion Valves at Westwood Terr and Westwood Forest - COMPLETE
January 2024 Knoll Street NW between Lewis St. & Nutley St. - COMPLETE
March 2024  Tapawingo Road SW between Lullaby Ln. & Plum St. - COMPLETE
March 2024 Albea Court NE and Park Street & Albea Court intersection COMPLETE
April 2024 Tapawingo Road and Glyndon Street SE VALVES COMPLETE
June 2024 Westview Court NE COMPLETE
July 2024 Tapawingo Road SW and Cottage Street SE VALVES COMPLETE
December 2024 Tapawingo Road SW between Lullaby Lane and Hillcrest Drive COMPLETE
January 2025 Beulah Road Lakeside Connection (Out of Town) COMPLETE
March 2025 Harmony Drive SW between Cottage Street and Plum Street COMPLETE
April 2025 Syracuse Circle (Out of Town) COMPLETE
May 2025 Berea Drive between Carnegie and Wesleyan (Out of Town) COMPLETE
June 2025 Wesleyan Drive (Out of Town) Berea to Cul-de-sac & stream COMPLETE
July 2025 Glyndon Street NE between Ayr Hill to Jean Place COMPLETE
July 2025 Glyndon Street SE between Adahi to Ayito COMPLETE
 August 2025 Center Street S between Dogwood and Moore PLANNED

This project would prepare a design to eliminate the existing ditch system and replace it with curb, gutter, drainage pipes and sidewalk along Wilmar Place, NW, from Lawyers Road to Center Street, N.  The storm drainage system must be designed to connect the existing storm drainage pipes from Lawyers Road to Dominion Road.  Construction funding for this project will be secured from a future bond issue and upon collection of future escrow funds.

Project Details

Project design budget:  $75,000

Project Manager:  John Jay Sergent

Anticipated construction date:  TBD - Town to apply for NVTA grant for construction

Wilmar Place NW Public Improvements Exhibit 3-5-2024(PDF, 1004KB)

Status Summary and Tentative Schedule





Completed DPW Project Archive

This sidewalk project will complete a gap between two existing sidewalks by adding approximately 600 feet of sidewalk between Glyndon Street NE and Beulah Road NE on the north side of Church Street.

Project Details

Project design budget:  $400,000

Project Manager:  Andrew Jinks, PE

Anticipated construction date:  Winter 2019

Church Street NE Sidewalk Extension Project Design(PDF, 11MB)

Status Summary and Tentative Schedule

Oct. 3, 2016 Town Council authorizes VDOT Revenue Sharing Grant Application
April 17, 2017 Town Council approves design contract
 June 17, 2017  Surveying begins
 February 2, 2018  50% design plans received
 Oct. 11, 2018  100% design complete
 November 2018  Advertise for construction
 Fall 2019  Construction complete

This project will replace the collapsed pedestrian bridge between the Freeman Store and W&OD Trail.

Project Details

Project design budget:  $174,000

Project Manager:  Andrew Jinks, PE

Anticipated completion date:  Fall 2023

Final Plan Set for Freeman Store Bridge(PDF, 9MB)

This proposed drainage improvement project will include curb and gutter and installation of storm drain pipes and curb inlet to resolve drainage issues on Moore Avenue, SE, between Spring Street and Park Street, SE.

Project Details

Project Budget:  $120,000

Project Manager:  Alan Chen, PE

Anticipated Start Date:  April 2023

Moore Avenue SE 100% Plans(PDF, 5MB)

Status Summary and Tentative Schedule

Sept. 26, 2022 Town Council awards design contract to Whitman, Requardt and Associates
October-November 2022 Survey crews are scheduled to be onsite 
 Oct. 18, 2023 Concept Design on-site Public Meeting
 March 14, 2024 Construction to begin
 April 2024 Construction Completed by US Concrete 

This project will replace existing asphalt trail with a concrete sidewalk and enclose the open roadway ditch on the northwest side of Old Courthouse Road, NE, from Gosnell Road to Pine Valley Drive.

Project Details

Project Budget: $1,200,000

Project Manager:  Andrew Jinks, PE

Anticipated Construction Date:  May 2022

Old Courthouse Road NE VIENNA Complete Set(PDF, 34MB)

Old Courthouse Road NE FAIRFAX Complete Set(PDF, 30MB)

Status Summary and Tentative Schedule

May 2022 Construction Begins
January 2023 Construction Complete
   
   
   
   
   
   
   

This project will complete the sidewalk along the east side of Park Street, NE, between Ayr Hill Avenue and Albea Court, NE.

Project Details

Project Design Budget:  $500,000

Project Manager:  Andrew Jinks, PE

Anticipated Construction Date:  Late 2024/Early 2025

Park Street NE Sidewalk:  Exhibit for July 21, 2020 Public Information Meeting(PDF, 4MB)

Park Street NE Sidewalk Construction Plan Set(PDF, 19MB)

Status Summary and Tentative Schedule

Oct. 3, 2016 Town Council authorizes VDOT Revenue Sharing Grant Application
May 7, 2018 Town Council approves design contract
July 2018 Surveying begins
Late 2022/Early 2023 Anticipated Construction
Summer 2023  Construction Complete

About the Maud Robinson Sidewalk Project

In February 2020, former Councilmember Maud Robinson provided the Town of Vienna with a generous gift of $7 million from her estate for the specific purpose of building sidewalks over a five-year period throughout the Town.

This generous fund is the origin for the Maud Robinson Sidewalk project—a project where the Town of Vienna is working with the Maud Ferris Robinson Charitable Trust to identify streets in the Town to install sidewalks.  One of the key requirements from the estate is to identify sidewalks where curb and gutter already exist.

The Town of Vienna currently has roughly 85 miles of sidewalk.  The Robinson bequest is expected to provide up to 3.3 miles in additional sidewalks throughout Town.

Importance of Sidewalks

Sidewalks are an important amenity for residents and for the community at large.  Sidewalks promote good health and pedestrian safety, connect individuals and destinations in the community, support Town businesses and sustainability goals.  Sidewalks will also continue to enhance the value of our community for years to come.

Project Updates: Staying Informed and Connected

The process of identifying streets for sidewalk installation has begun and we want to hear directly from citizens in our community.  The Town Council is currently considering recommendations and looking to make final decisions about locations for sidewalk installation.  Residents who live on selected and recommended streets will be given many opportunities to provide feedback.  Below are ways for you to get involved, learn more about the project, and share your comments, concerns, and questions about the project:

From the May 10, 2021 Town Council Conference Session Meeting Minutes:

Plan Moving Forward with the Maud Robinson Trust for Sidewalks

Mayor Colbert called on Mike Gallagher, Director, Public Works to present the first
item for discussion.  Outreach has been initiated on all of the original list of 24
projects.  Four are in final design, nine projects have been authorized for design with
the condition to obtain specific approval of the project before pursuing final design,
four are not recommended by DPW, one was not authorized for design (Melody Ln SE
from Lullaby to the end of the street) and six projects require more outreach.

DPW is in the process of compiling a larger comprehensive list, including street
segments submitted to DPW for consideration, to determine all street projects that
are eligible for, and meet the Robinson funding criteria.  So far, six streets have been
added by request: Church Street NE, Ware Street SW, Glen Ave SW, Cottage Street SW,
Frederick Street SW, and Adahi Road SE. DPW will use this comprehensive list to
determine which streets can be added.

Four projects that will be constructed by the end of calendar year 2021: Cabin Road
SE, Plum Street SW, Holmes Drive NE, and Pleasant Street SW. Pleasant Street SW was
not a project on an initial list; it was shelved, shovel ready, in 2015 due to depletion
of the Walk to Downtown federal funding. Staff specifically requested and received,
approval from the Trust, to construct this project.

The 2022 projects have been divided into four groups with varying start dates.  A
nine-month design phase prefaces the actual construction phase.  It was pointed out
that Group 1 will need to be authorized by Council in early June of this year.

Responses to Key Council comments/concerns are summarized as follows:

• Transparency is critical; all attachments to this presentation should be posted
   to the website;
• Need to pick up pace of work; funding ends fall 2024; post to website;
• Street scoring data, categorization and notes will be made public;
• Every street throughout Vienna physically assessed (275 streets) against
   original criteria; added 13 new projects (six Cul-de-sacs); Cul-de-sacs are lower
   priority, will be considered at a later date;
• Street selection largely based upon amount of traffic and overall safety, as well
   as connectivity (missing link projects -14 identified);
• Five of original 29 projects identified potentially qualify for CARES funding in
   conjunction with Robinson funds;
• Determination of side of street will be achieved within the nine-month design
   phase; deliberate process in order to satisfy concerns of residents;
• Side of street consideration will include impact on trees; grading on private
   property; resident responses; constructability; connectivity; cost; etc.
• Trust does not address side of street issue, consider approaching Trustee
   regarding side walk on both sides of busiest streets;
• Residents of identified streets will be notified of status and invited to submit
   comment.

Public Hearing on Maud Robinson Sidewalk Project

On Monday, April 26, Town Council held a public hearing to solicit feedback from residents about the project.  The public hearing was recorded and may be viewed online.

Email Town Staff

Have questions or comments about the project?  Send them via email to dpw@viennava.gov

 Learn More About the Sidewalk Project Locations

 

This proposed traffic-calming, bioretention project will include curb-extension design and installation for the intersections of Tapawingo Road, SW,  and Kingsley Road, SW, at Meadow Lane SW.

Project Details

Project Design and Construction Budget:  $340,000

Project Manager:  Alan Chen, PE

Anticipated Construction Date:  June 2023

Intersections of Tapawingo and Kingsley Roads, SW at Meadow Lane SW Plan(PDF, 22MB)

Nov. 3, 2021 Exhibit(PDF, 3MB)

Status Summary and Tentative Schedule

October 2018 Town Council awards design contract to Urban, LTD
July 2019  Initial concept plans received
Nov. 19, 2019 Tapawingo Road, SW intersection community design meeting to discuss concept plan
Nov. 20, 2019 Kingsley Road, SW intersection community design meeting to discuss concept plan
Nov. 3, 2021 Community Information Meeting to discuss latest design plan
April 24, 2023 Town Council approved the construction contract and approve amended funding agreement
 September 2023  Construction Complete

This intersection has two traffic poles with long mast arms holding signal heads at a diagonal, which does not line up with traffic lanes.  Separate left-turn lights have been added, which puts extra strain on the poles.  A Virginia Department of Transportation (VDOT) Congestion Mitigation and Air Quality (CMAQ) grant will allow the Town of Vienna to replace the traffic signals at this intersection with a four-pole configuration with underground wiring and pedestrian-audible countdown signals.

Project Details

Project Budget:  $900,000

Project Manager:  Andrew Jinks, PE

Anticipated Construction Date:  Spring/Summer 2022

Final Design Plans(PDF, 2MB)

Title of the Table Goes Here

Sept. 13, 2010 Town Council approves application for a VDOT CMAQ grant
Feb. 16, 2012 Pre-scoping meeting held to determine project objectives
 March 6, 2012 Proposal for engineering services received
April 16, 2012 Town Council awards design contract to Rinker Design Associates
 Nov. 12, 2012 Acquiring easements
 April 17, 2015 Design suspended until construction funding secured
 October 2016 Town Council approves $900,000 NVTA grant
Oct. 24, 2016 Town awards consulting contract to Rinker Design for final engineering and ROW acquisition services
February 2018 Request VDOT to authorize ROW acquisition phase of project
 Fall 2023  Construction complete

Improvements will consist of extending the storm drainage system from the intersection of Branch Avenue, SE, and Valley Drive, SE, and down Branch Avenue, SE, to improve stormwater drainage in the area.

Project Details

Project Design and Construction Budget:  $330,000

Project Manager:  Alan Chen

Anticipated Start Date:  

100% Design Plan - 600 Block Valley Drive SE Storm Drainage Improvements(PDF, 6MB)

September 2021 Urban, Ltd. completed survey
July 13, 2022 Citizen information meeting to discuss latest design plan
August 2022 100% design plan completed
March 6, 2023 Council approved construction contract
September 2023 Resumption of construction after gas utility conflict resolution
 October 2023  Construction completed

To correct flooding of businesses, this project installs a storm sewer at Nutley Street NW and Maple Avenue W.

Project Details

Project Budget:  $375,000

Project Manager:  Christine Horner, PE

Anticipated Construction Date:  TBD

Status Summary and Tentative Schedule

June 18, 2012 Town Council approves contract for drainage study
January 15, 2013 On-site property owner meeting
 May 19, 2014 Town Council considers award of final design contract
 January 16, 2015 Concept plans received - under review 
 April 21, 2015 On-site property owner meeting
 September 28, 2015 Town Council awards additional design funds for downstream study

2017 transportation planning process

Regional projects