Water Main and Appurtenance Improvements
Improvements will consist of a new water meter installation, repairs to aging infrastructure, and provisions to increase functionality of the Town's water system.
Project Details
Project Construction Budget: $2,500,000
Project Manager: frank.torre@viennava.gov
Status Summary and Tentative Schedule
| July 2024 |
Tapawingo Road,SW, and Cottage Street, SE, VALVES COMPLETE |
| December 2024 |
Tapawingo Road, SW, between Lullaby Lane and Hillcrest Drive COMPLETE |
| January 2025 |
Beulah Road Lakeside Connection (Out of Town) COMPLETE |
| March 2025 |
Harmony Drive, SW, between Cottage Street and Plum Street COMPLETE |
| April 2025 |
Syracuse Circle (Out of Town) COMPLETE |
| May 2025 |
Berea Drive between Carnegie and Wesleyan (Out of Town) COMPLETE |
| June 2025 |
Wesleyan Drive (Out of Town) Berea to cul-de-sac & stream COMPLETE |
| July 2025 |
Glyndon Street, NE, between Ayr Hill to Jean Place COMPLETE |
| July 2025 |
Glyndon Street, SE, between Adahi to Ayito COMPLETE |
| August 2025 |
Center Street, S, between Dogwood and Moore COMPLETE |
| September 2025 |
Tapawingo Road, SW, between Meadow and Ware COMPLETE |
| October 2025 |
Tapawingo Road, SW, between Ware and Frederick COMPLETE |
| November 2025 |
Memory Court (out of Town) COMPLETE |
| February 2026 |
Plum Street, SW, between Harmony and Tapawingo PLANNED |
| March 2026 |
Timber Lane, SW, between Harmony and Tapawingo PLANNED |