Water Main and Appurtenance Improvements
Improvements will consist of a new water meter installation, repairs to aging infrastructure, and provisions to increase functionality of the Town's water system.
Project Details
Project Construction Budget: $2,500,000
Project Manager: frank.torre@viennava.gov
Status Summary and Tentative Schedule
July 2023 |
Dogwood Street SW - between Cottage St. & Center St. - COMPLETE |
August 2023 |
Pruitt Court SW - Ware Street to cul-de-sac - COMPLETE |
August 2023 |
Old Courthouse Road Check Valve and Vault - COMPLETE |
October 2023 |
Hillcrest Drive SW between Tapawingo Rd. & Kingsley Rd. - COMPLETE |
December 2023 |
Polly Street SE between Wolftrap Dr. & Kramer Dr. - COMPLETE |
January 2024 |
Wolftrap Road Insertion Valves at Westwood Terr and Westwood Forest - COMPLETE |
January 2024 |
Knoll Street NW between Lewis St. & Nutley St. - COMPLETE |
March 2024 |
Tapawingo Road SW between Lullaby Ln. & Plum St. - COMPLETE |
March 2024 |
Albea Court NE and Park Street & Albea Court intersection COMPLETE |
April 2024 |
Tapawingo Road and Glyndon Street SE VALVES COMPLETE |
June 2024 |
Westview Court NE COMPLETE |
July 2024 |
Tapawingo Road SW and Cottage Street SE VALVES COMPLETE |
December 2024 |
Tapawingo Road SW between Lullaby Lane and Hillcrest Drive COMPLETE |
January 2025 |
Beulah Road Lakeside Connection (Out of Town) COMPLETE |
March 2025 |
Harmony Drive SW between Cottage Street and Plum Street COMPLETE |
April 2025 |
Syracuse Circle (Out of Town) COMPLETE |
May 2025 |
Berea Drive between Carnegie and Wesleyan (Out of Town) COMPLETE |
June 2025 |
Wesleyan Drive (Out of Town) Berea to Cul-de-sac & stream COMPLETE |
July 2025 |
Glyndon Street NE between Ayr Hill to Jean Place COMPLETE |
July 2025 |
Glyndon Street SE between Adahi to Ayito COMPLETE |
August 2025 |
Center Street S between Dogwood and Moore PLANNED |