Project Details
Project Design and Construction Budget: $340,000
Project Manager: Alan Chen, PE
Anticipated Construction Date: June 2023
Intersections of Tapawingo and Kingsley Roads, SW at Meadow Lane SW Plan(PDF, 22MB)
Nov. 3, 2021 Exhibit(PDF, 3MB)
Status Summary and Tentative Schedule
October 2018 |
Town Council awards design contract to Urban, LTD |
July 2019 |
Initial concept plans received |
Nov. 19, 2019 |
Tapawingo Road, SW intersection community design meeting to discuss concept plan |
Nov. 20, 2019 |
Kingsley Road, SW intersection community design meeting to discuss concept plan |
Nov. 3, 2021 |
Community Information Meeting to discuss latest design plan |
April 24, 2023 |
Town Council approved the construction contract and approve amended funding agreement |
September 2023 |
Construction Complete |