Nutley Street Culvert Project

This project mitigates flooding issues associated with the existing undersized culvert and the proposed design will replace the existing culvert with twin 10-foot by 6-foot culverts.  This project will involve modification of traffic and lane closures along Nutley Street SW from February 2026 to January 2027.

Project Details

Project Budget:  $1,600,000

Project Manager:  Alan Chen, PE

Anticipated Construction Date:  Feb. 16, 2026

Nutley Street SW Culvert Plans(PDF, 19MB)

Status Summary and Tentative Schedule

June 2012 Town Council approves contract for drainage study
March 21, 2013 On-site citizen meeting
Nov. 18, 2013 Town Council awards final design contract
July 10, 2014 60% plans received 
Nov. 20, 2014 On-site citizen meeting
May 8, 2015 Design reviewed by VDOT
Aug. 21, 2015  On-site citizen final plan review
March 7, 2016 Town Council approves funds for additional hydraulic analysis
March 2017 Pending future CIP funding
June 2024 Design restarted with anticipated start of construction late in 2024
October 2024 100% Design completed and Town Council meeting scheduled for funding
December 2024 Construction contract awarded and initial site preparation to begin. 
Summer 2025 Construction to begin upon receipt of pending VDOT permit approval.
February 2026 Construction start
 January 2027  Anticipated construction completion