Nutley Street Culvert Project
This project mitigates flooding issues associated with the existing undersized culvert and the proposed design will replace the existing culvert with twin 10-foot by 6-foot culverts. This project will involve modification of traffic and lane closures along Nutley Street SW from February 2026 to January 2027.
Project Details
Project Budget: $1,600,000
Project Manager: Alan Chen, PE
Anticipated Construction Date: Feb. 16, 2026
Nutley Street SW Culvert Plans(PDF, 19MB)
Status Summary and Tentative Schedule
| June 2012 |
Town Council approves contract for drainage study |
| March 21, 2013 |
On-site citizen meeting |
| Nov. 18, 2013 |
Town Council awards final design contract |
| July 10, 2014 |
60% plans received |
| Nov. 20, 2014 |
On-site citizen meeting |
| May 8, 2015 |
Design reviewed by VDOT |
| Aug. 21, 2015 |
On-site citizen final plan review |
| March 7, 2016 |
Town Council approves funds for additional hydraulic analysis |
| March 2017 |
Pending future CIP funding |
| June 2024 |
Design restarted with anticipated start of construction late in 2024 |
| October 2024 |
100% Design completed and Town Council meeting scheduled for funding |
| December 2024 |
Construction contract awarded and initial site preparation to begin. |
| Summer 2025 |
Construction to begin upon receipt of pending VDOT permit approval. |
| February 2026 |
Construction start |
| January 2027 |
Anticipated construction completion |