Moore Avenue SE Drainage Improvements
This proposed drainage improvement project will include curb and gutter and installation of storm drain pipes and curb inlet to resolve drainage issues on Moore Avenue, SE, between Spring Street and Park Street, SE.
Project Details
Project Budget: $120,000
Project Manager: Alan Chen, PE
Anticipated Start Date: April 2023
Moore Avenue SE 100% Plans(PDF, 5MB)
Status Summary and Tentative Schedule
Sept. 26, 2022 |
Town Council awards design contract to Whitman, Requardt and Associates |
October-November 2022 |
Survey crews are scheduled to be onsite |
Oct. 18, 2023 |
Concept Design on-site Public Meeting |
March 14, 2024 |
Construction to begin |
April 2024 |
Construction Completed by US Concrete |