Manvell Road, SE, Drainage Improvements

In September 2010, following a public hearing, Town Council authorized application to the Virginia Department of Transportation (VDOT) for a Congestion Mitigation and Air Quality (CMAQ) grant to complete sidewalks on all streets within a one-mile radius of the Vienna Metro Station.  This is a federal grant that assists in completing projects that are regionally significant and provide transportation options to facilitate the use of mass transit.

This project completes all missing sections of sidewalk along Kingsley Road, SW, from Nutley Street to DeSale Street, SW.

Project Details

Project Budget:  TBD

Project Manager:  Andrew Jinks, PE

Anticipated construction date:  Not scheduled at this time

Status Summary and Tentative Schedule

September 2010 Town Council approves application for a VDOT CMAQ grant
April 9, 2012 Proposal for engineering services received
May 7, 2012  Town Council awards design contract to Rinker Design Associates
Dec. 15, 2014 Town Council consideration of CMAQ construction grant
December 2016 On hold pending future funding
October 2022 Restart design
Summer 2024 Begin right-of-way negotiations
Summer 2025 Complete coordination of pole relocation with Dominion Energy
October 2025 Anticipated start of construction