Manvell Road, SE, Drainage Improvements

Manvell Road SE has significant recurring stormwater drainage issues between Park Street SE and Glyndon Street SE.  This project includes 715' of concrete curb and gutter along the west side of the street with five storm drain inlets and about 195' of storm drain sewers to alleviate the drainage issues.  Additionally, the project also includes 330' of curb, gutter and sidewalk along the east side of the street, which will connect existing sidewalk on Park Street SE and Manvell Road SE.  The project is pending utility coordination and construction is anticipated to begin in early spring 2026.

 

 

Project Details

Project Budget:  TBD

Project Manager:  John Jay Sergent, PE

Anticipated construction date:  Spring 2026

Status Summary and Tentative Schedule

September 2010 Town Council approves application for a VDOT CMAQ grant
April 9, 2012 Proposal for engineering services received
May 7, 2012  Town Council awards design contract to Rinker Design Associates
Dec. 15, 2014 Town Council consideration of CMAQ construction grant
December 2016 On hold pending future funding
October 2022 Restart design
Summer 2024 Begin right-of-way negotiations
Summer 2025 Complete coordination of pole relocation with Dominion Energy
Spring 2026 Anticipated start of construction