Church Street NE (Park to Glyndon) and Glyndon Street NE (Maple to Ayr
This project will provide a new curb, gutter, and sidewalk on both sides of Church Street NE between Park Street and Glyndon Street and both sides of Glyndon Street from Maple Avenue to Ayr Hill Avenue. A separate roadway and drainage project on Glyndon Street from Ayr Hill Avenue to Jean Place will connect to this project.
Project Budget: $600,000
Contact: DPW@viennava.gov
Anticipated Construction Date: 2025
Link to Concept Plan - July 2025(PDF, 14MB)
Status Summary and Tentative Schedule
April 14, 2021 |
Approval of Project Funding (NVTA Funds) |
August 13, 2025 |
Public Meeting to Present Design |
Early 2026 |
Town Council Approval of Construction Contract |
2026 |
Construction Start |