Church Street NE (Park to Glyndon) and Glyndon Street NE (Maple to Ayr

This project will provide a new curb, gutter, and sidewalk on both sides of Church Street NE between Park Street and Glyndon Street and both sides of Glyndon Street from Maple Avenue to Ayr Hill Avenue. A separate roadway and drainage project on Glyndon Street from Ayr Hill Avenue to Jean Place will connect to this project.

638828090969800000.jpg

 

Project Budget:  $600,000

Contact:  DPW@viennava.gov

Anticipated Construction Date:  2025

Church Street NE Roadway and Sidewalk Improvements - link to 95% plan(PDF, 20MB)

 

 

 

 

 

Status Summary and Tentative Schedule

April 14, 2021 Approval of Project Funding (NVTA Funds)
July 2025 Design Complete
Summer 2025 Public Meeting to Present Design
Summer 2025 Town Council Approval of Construction Contract
Late 2025 Construction Start