Ayr Hill Avenue, NW Traffic Calming at Lawyers Road Intersection
Main improvement includes bumping out the curb ramps located at the Ayr Hill Avenue leg of the Ayr Hill Avenue and Lawyers Road intersection. This improvement may also include adding some curb and gutter along Ayr Hill Avenue near the intersection, replacing/adding sidewalk, adding driveway aprons, and on-street parking lines where applicable. This will create a narrowing of Ayr Hill Avenue within the area of the intersection and also create a safer environment for pedestrians.
Project Details:
Project Manager: Andrew Jinks, PE
Project Status: Under Design
Anticipated Construction Start Date: Spring/Summer 2026
Fall 2024 |
Design Begin |
Spring 2025 |
60% Design |
Winter 2025 |
100% Design Complete |
Spring/Summer 2026 |
Construction Begins |
Fall 2026 |
Construction Complete |