Nutley Street and Marshall Road SW Drainage Improvements
This project replaces the culvert under Nutley Street, SW, between Kingsley and Marshall roads, SW.
Project Details
Project Budget: $500,000
Project Manager: Alan Chen, PE
Anticipated Construction Date: TBD
Nutley Street SW Culvert Plans(PDF, 19MB)
Status Summary and Tentative Schedule
June 2012 |
Town Council approves contract for drainage study |
March 21, 2013 |
On-site citizen meeting |
Nov. 18, 2013 |
Town Council awards final design contract |
July 10, 2014 |
60% plans received |
Nov. 20, 2014 |
On-site citizen meeting |
May 8, 2015 |
Design reviewed by VDOT |
Aug. 21, 2015 |
On-site citizen final plan review |
March 7, 2016 |
Town Council approves funds for additional hydraulic analysis |
March 2017 |
Pending future CIP funding |
June 2024 |
Design restarted with anticipated start of construction late in 2024 |
October 2024 |
100% Design completed and Town Council meeting scheduled for funding |