Park Street SE/Locust Street SE
Park and Locust Streets SE Intersection Improvements
The Park and Locust streets intersection provides unique and complex challenges in terms of traffic control and pedestrian safety. It is a high-volume intersection during certain hours of the day, and landscaping surrounding the intersection can block the sight-line for motorists who wish to make a turn onto Park Street SE from Locust Street SE. Often motorists must impede the crosswalk on Locust Street in order to see far enough down Park Street to turn safely, which creates a dangerous situation for pedestrians.The TSC recommended that Council approve construction of a mini roundabout at the intersection of Park and Locust streets. Construction of the mini roundabout is scheduled to begin August 1, 2016.

Project Details
Project Budget:  $490,000
Project Manager:  Luis Blandon
Anticipated Construction Date:  August 2016


August 11, 2014 Federal Highway Demonstration Grant Application
September 9, 2014 Congressman Connolly Support Letter 
March 31, 2015 Grant Approved
April 27, 2015  Design contract award
June 24, 2015  60% plan received
June 26, 2015  Right of Entry letters sent to adjacent property owners 
September 25, 2015 Construction contract advertised
October 16, 2015  Bid opening 
February 8, 2016 All bids over budget, solicitation canceled
February 22, 2016  Preparing bids allowing for short street closure
April 14, 2016 Rebid advertised
May 10, 2016 Bid opening
July 11, 2016 Contractor award
August 1, 2016 Begin construction
August 19, 2016 Construction complete
August 22, 2016 Post-construction evaluation begins
October 2016 Complete