This sidewalk project completes the missing section of sidewalk on Maple Avenue E - service drive - between Saratoga Waye and Westbriar Drive NE. The Walk to Downtown Initiative completes sidewalks within the first block of Maple Avenue, Vienna's commercial corridor, to provide safe routes for residents to walk to businesses, restaurants and bus stops.

Project Details

Project Budget: $365,000
Project Manager: Luis Blandon
Anticipated construction date: Spring 2014

Maple Avenue E Service Drive Walkway Plan

Status Summary and Tentative Schedule
November 5, 2012 Town Council authorized Walk to Downtown Grant Application
January 14, 2013 Town Council award of survey and design contract
November 1, 2013  Preparing bid 
November 7, 2013 Plan sent of property owners along service road
December 18, 2013 Bid opening
January 27, 2014 Town Council award of construction contract
March 10, 2014 Construction start
July 1, 2014  Construction complete