Traffic Signal - Nutley Street and Courthouse Road
This intersection has two traffic poles with long mast arms holding the signal heads at a diagonal, which does not line up with traffic lanes. Separate left-turn phase traffic lights have been added, which puts extra strain on the poles as well. The Virginia Department of Transportation (VDOT) Congestion Mitigation and Air Quality (CMAQ) grant allows the Town of Vienna to replace the traffic signals at this intersection with a 4-pole configuration with underground wiring and pedestrian audible countdown signals.

Project Details

Project Budget: $700,000
Project Manager: Luis Blandon
Anticipated construction date: Spring 2014

Traffic Signal Plans Nutley and Courthouse Road Final

Status Summary and Tentative Schedule
September 13, 2010 Town Council approved application for a VDOT CMAQ grant
February 16, 2012 Pre-scoping meeting held to determine project objectives
March 6, 2012 Proposal for Engineering Services received
April 16, 2012 Town Council awarded design contract to Rinker Design Associates
October 16, 2012 Easements acquired
February 28, 2013 Construction contract advertised
September 5, 2013 Bid Advertised
October 3, 2013 Bid Opening
December 16, 2013 Construction contract award postponed
January 6, 2014 Construction contract award
April 16, 2014  Construction Start
August 4, 2014  Requested Dominion Power cut-over to new signal
December 9, 2014  Signal base energized, work begins again 
April 17, 2015  Complete