Walk to Metro - Marshall Road SW
In September 2010, Town Council authorized application to the Virginia Department of Transportation (VDOT) for a Congestion Mitigation and Air Quality (CMAQ) grant to complete sidewalks on all streets within a one-mile radius of the Vienna MetroRail Station. This is a federal grant to assist in completing projects that are regionally significant and provide transportation options to facilitate the use of mass transit.

This project is adjacent to an elementary school and provides a safe path for children to walk or bike to school.The project replaces the existing asphalt path with a permanent concrete sidewalk on Marshall Road SW from Marshall Road Elementary School to Trowbridge Place SW.

Project Details

Project Budget: $1.6 Million
Project Manager:  Luis Blandon
Anticipated construction date: Spring 2017

Marshall Road SW Plan

Status Summary and Tentative Schedule
September, 2010 Town Council approved application for a VDOT CMAQ grant
April 9, 2012 Proposal for Engineering Services received
May 7, 2012 Town Council awarded design contract to Rinker Design Associates
October 20, 2014 Town Council approved extra design funds
August 1, 2016 Additional VDOT revenue sharing and NVTA funding received
September 16, 2016 Right of Entry letters mailed
October 6, 2016 Citizen Meeting held
December 8, 2016 Final Plans Received
March 2017 Preparing environmental review
April 3, 2017 Town Council awards construction project
March 26, 2018 Construction begins
August 2018 Substantial completion
September 11, 2018 Ribbon Cutting