Cottage Street SW - Walk to Metro
In September 2010, after a public hearing,Town Council authorized applying to the Virginia Department of Transportation (VDOT) for a Congestion Mitigation and Air Quality (CMAQ) grant to complete sidewalks on all streets within a one-mile radius of the Vienna MetroRail Station. This is a federal grant to assist in completing projects that are regionally significant and provide transportation options to facilitate the use of mass transit.

This project completes the sidewalk on the west side of Cottage Street SW from Moore Avenue to Kingsley Road. One lane in portions of Tapawingo Road and/or Cottage Street will be periodically closed, and traffic will be managed by flaggers. Also, parallel parking will be closed daily during the hours of operation. Access to driveways should not be affected by the construction.

Project Details

Project Budget: $600,000
Project Manager:  Dennis Johnson
Construction Manager: Luis Blandon
Construction Contractor:  Sagres Construction, Corp.
                                     Ron Grob, Project Manager 703-924-7220
Anticipated construction start date: February 9, 2015
Anticipated construction end date: Mid October 2015

Cottage Street SW Moore to Kingsley Plan

Status Summary and Tentative Schedule
September, 2010 Town Council approved application for a VDOT CMAQ grant
April 9, 2012 Proposal for Engineering Services received
May 7, 2012 Town Council awarded design contract to Rinker Design Associates
January 28, 2013 Extra storm sewer design authorized
February 22, 2013 Acquiring temporary construction easements
July 31, 2013  Preparing bid package
September 2, 2014  Construction bid advertised
October 7, 2014  Bid opening
January 5, 2015  Construction contract award 
January 27, 2015  Preconstruction meeting 
January 29, 2015 Preconstruction property owner letter
February 9, 2015  Construction start
August 14, 2015  Complete pending landscaping
November 13, 2015  Complete