In September 2010, Town Council authorized applying to the Virginia Department of Transportation (VDOT) for a Congestion Mitigation and Air Quality (CMAQ) grant to complete sidewalks on all streets within a one-mile radius of the Vienna MetroRail Station. This is a federal grant to assist in completing projects that are regionally significant and provide transportation options to facilitate the use of mass transit.  The project constructs sidewalk, curb, gutter and drainage improvements on Courthouse Road SW from Nutley Street to the Town line near the Dog Park.

Project Details

Project Budget: Will be built with the Traffic Signal project
Project Manager: Luis Blandon
Anticipated construction date: Spring 2014

Courthouse Road SW Walk to Metro Plan

Status Summary and Tentative Schedule
September, 2010 Town Council approved application for a VDOT CMAQ grant
April 9, 2012 Proposal for Engineering Services received
May 7, 2012 Town Council awarded design contract to Rinker Design Associates
January 14, 2013 Acquiring Temporary Construction Easements
March 2013 Preparing construction bid documents 
September 5, 2013 Bid Advertised with Courthouse and Nutley Traffic Signal
October 3, 2013 Bid Opening
December 16, 2013 Construction contract award postponed
January 6, 2014  Construction contract award 
April 16, 2014 Construction Start
May 1, 2015  Complete