Project budget:  $500,000
Project Manager:  Dennis Johnson, P.E.
Anticipated construction date: Summer 2014

Status Summary and Tentative Schedule
April 25, 2011  Applied for VDOT FY 2012 Revenue Sharing Funding 
February 2012  Grant approved
May 21, 2012 Bid preparation contract approved
October 10, 2013 Bid Opening
December 16, 2013 Contract award
June 2014  Anticipated start date 
June 13, 2014  Pre-construction meeting with adjacent property owners
July 7, 2014 Construction start
August 22, 2014  Construction complete