Nutley Street NW Sidewalk Project
This project entails construction of a new sidewalk on west side of Nutley Street NW, between Maple Avenue W and Windover Avenue NW.

Project Details
Project budget:  $100,000
Project Manager:  Dennis Johnson, P.E.
Anticipated construction date: 2012

Status Summary and Tentative Schedule
September 2009
Town Council authorized applying for Congestion Mitigation and Air Quality grant.
April 2011
Project administration agreement approved.
February 8, 2012 Sent letters to property owners regarding surveying for the project.