Town Hall HVAC Project
This project entails construction and installation of new HVAC system, ceiling, lights, carpet and windows.

Project Details
Project budget:  $1,500,000
Project Manager:  John Jay Sergent
Design Consultant: Wiley|Wilson
Anticipated construction date: 2012

Project Specifications
Project Construction Drawings
Project Addendum 1

Renovation Information

Status Summary
September 13, 2010 Town Council awarded design contract
November 8, 2010 Town Council held project work session
November 17, 2010 Town Council toured St. Peter & Paul VI VAV system installation
December 13, 2010 Town Council held project work session
January 3, 2011 Town Council toured Alexandria Schools VAV installations
February 14, 2011 Town Council held project work session; approved VAV option
October 22, 2012 Construction contract award
January 2013 Construction begins
May 1, 2014  Substantial completion