Saint Roman's Drive Pipe Stem Water Line Replacements
This project entails replacing non-standard sized water mains in the four private driveways to the pipe-stem lots along Saint Roman's Drive.

Project Details
Project budget:  $200,000
Project Manager:  Seth Haffner
Anticipated construction date: Fall 2014

Status Summary and Tentative Schedule
May 9, 2011 Town Council awarded construction contract
May 31, 2011 Awaiting VDOT permit
March 3, 2014  Preparing bid documents
May 12, 2014  Contract canceled;  new contract awarded.
June 9, 2014  Construction start
October 10, 2014 Complete