Maple Avenue Banner Pole Replacement
This project entails removing old cabling from the wooden pole near the Whole Foods store and installing a new foundation and steel pole to hold banners placed over Maple Avenue.

Project Details
Project budget:  $8,000
Project Manager:  Dennis Johnson, P.E.
Anticipated construction date: January 2011

Status Summary and Tentative Schedule

July 16, 2010

Town Council awarded construction contract

October 1, 2010

Special pole delivered

November 1, 2010

Foundation design approved

December 20, 2010

Test pits dug, irrigation lines relocated

April 3, 2011

Acquiring easement

October 2011 Foundation and pole installed