Dogwood Street SW Sidewalk
This project entails construction of a new sidewalk in the public right-of-way on the north side of Dogwood Street SW.

Project Details

Project budget:  $60,000
Project Manager:  Dennis Johnson, P.E.
Construction Manager:  Dennis Johnson, P.E.
Anticipated construction date: March 2011

Status Summary and Tentative Schedule

October, 2007

Notification of available funds

April 28, 2008

Submitted request to administer project to VDOT

July 8, 2008

VDOT approved request to administer project

April 10, 2009

Submitted VDOT form EQ-121: Hazardous Materials

April 27, 2009

Submitted VDOT form EQ-555: Water Quality and Natural Resources

May 4, 2009

VDOT completed cultural resources review

June 16, 2009

VDOT issued environmental categorical exclusion

June 22, 2009

Posted notice of willingness to hold a public hearing

July 31, 2009

Public hearing notice and letter sent to homeowners

July 31, 2009

Dogwood Street SW sidewalk plans

August 4, 2009

Construction contract bid opening

August 17, 2009

Town Council holds public hearing and approves sidewalk on north side of Dogwood Street SW

September 13, 2009

Town Council awarded construction contract to Espina Paving

January 3, 2011

Construction postponed until March

March 28, 2011

Construction started

April, 2011

Construction completed

April 26, 2011

Ribbon cutting ceremony held

November 18, 2011

Trees planted