Harmony Drive SE and Lullaby Lane S Sidewalk Project
The Cunningham Park Elementary School developed a 2011 School Travel Plan after an extensive survey of families with student walkers and input from Fairfax Public Schools and Town staff. The Plan's purpose is to encourage children to walk and bicycle to school; to make bicycling and walking to schools a safer and more appealing transportation alternative, thereby encouraging a healthy and active lifestyle from an early age; and to facilitate the planning, development and implementation of project and activities that will improve safety and reduce traffic, fuel consumption and air pollution in the vicinity of schools.

The Cunningham Park Elementary Travel Plan suggested several projects, with the top priority construction of new sidewalk, ADA ramps and crosswalk on one side of Harmony Drive SW, between Park and Lullaby Lane. During the Public Hearing, Town Council added another top priority, a new sidewalk on the east side of Lullaby Lane SW from Harmony to Tapawingo to provide a route for children all the way to the existing sidewalk on Tapawingo Road. After endorsement by the Vienna Town Council, a VDOT Safe Routes to School grant has been approved for the project.

This project entails construction of a new sidewalk on the north side of Harmony Drive SE, between Park Street SE and Lullaby Lane S. The additional sidewalk construction extends up Lullaby Lane S from Harmony Drive SE to Tapawingo Road SE.

Project Details
Project budget:  $150,000
Project Manager:  Dennis Johnson
Construction Manager: Luis Blandon
Anticipated construction date: Summer 2014

Harmony and Lullaby Sidewalk Plan

Status Summary and Tentative Schedule
May 23, 2011 Town Council authorized applying for Safe Routes to School sidewalk grant
January 31, 2012 VDOT notified the Town by letter that the grant was approved
August 20, 2012 Town Council award of design contract
March 2013  Acquiring Easements
September 2013 Preparing Bid
June 4, 2014  Bid Opening
August 18, 2014  Construction contract award
October 20, 2014  Construction begins
December 19, 2014  Construction complete, awaiting spring tree planting
April 3, 2015  Complete