Hill Top Road NE, Park Street to Glyndon Street Sidewalk Project
This project entails construction of a new sidewalk on one side of Hill Top Road NE, between Park Street NE and Glyndon Street NE.

Project Details
Project budget:  $60,000
Project Manager:  Dennis Johnson, P.E.
Anticipated construction date: 2010

Status Summary and Tentative Schedule
June 7, 2010  Town Council awarded design contract 
September 13, 2010  Town Council extended design contract to include the Glyndon Street side 
January 5, 2011 4PM  Citizen design review 
March 4, 2011  Letters sent requesting temporary construction easements 
June 6, 2011  Town Council awarded construction contract 
September 2011  Construction complete, awaiting tree planting 
November 2011  Complete