DeSale Street South Street and Sidewalk Reconstruction
The DeSale Street South Street and Sidewalk Reconstruction project will reconstruct the street, curb, gutter and sidewalks in the existing location.

Project Details
Project budget:  $1,210,000 with 50% funding from VDOT
Project Manager:  Dennis Johnson, P.E.
Construction Inspector: Anne Burkhardt, P.E.
Anticipated construction date: Spring 2011

Status Summary and Tentative Schedule

September 14, 2009

Town Council endorsed VDOT Revenue Sharing application 

September 15, 2009

Application submitted

October 30, 2009

VDOT approved Request to Administer Project

March 17, 2010

Began acquisition of temporary construction easements

January 6, 2011

Mandatory pre-bid meeting held

February 9, 2011

Construction contract bid opening

March 21, 2011

Town Council awarded construction contract

April 25, 2011

Construction started

November 2011  Construction complete 
November 16, 2011 Ribbon Cutting Ceremony at 3 p.m. 
November 18, 2011  Trees planted