Maple Avenue West Streetscape Project
This project entails installation of brick pavers, landscaping and other streetscape options from the Lawyers Road/Courthouse Road intersection to the western Town boundary. This will harmonize the overall appearance of Maple Avenue as the current eastern and western halves of Maple Avenue do not match each other.

Project Details
Project budget:  $8,000,000 for full project
Project Manager:  Dennis Johnson
Construction Manager: Luis Blandon
Design consultant: Bowman Consulting
Survey and design status: Design underway
Right-of-way and utility status: Underway
Anticipated construction date: Full project schedule not determined; awaiting funding.
VDOT Maple Avenue Phase 4A

Status Summary and Tentative Schedule

May, 2009

VDOT funding authorization

May, 2009

Town Council awarded engineering services contract

June, 2009

Predesign and designer tour

September 21, 2009

Concept and alternative review with Town Council

March 8, 2010

30% design Town Council workshop

March 15, 2010

Town Council meeting held to decide design options

November 1, 2010

Easement acquisition begins

July 11, 2011

Using available funding, mid-block signal and gateway design authorized by Town Council

November 19, 2012  Town Council authorized construction contract with available funds
August 22, 2013 Bid opening
October 28, 2013  Town Council award of construction contract
February 3, 2014  Construction start
February 4, 2015  Complete