Plum Street SW and Harmony Drive SW
This project entails installing new sidewalks along Plum Street SW and Harmony Drive SW.

Project Details
Estimated cost:  $300,000
Project Manager:  Dennis Johnson, P.E.

Status Summary and Tentative Schedule

 September 14, 2009

Town Council approved grant funding agreement

 December 7, 2009

Town Council awarded design contract

 November 5, 2010

Letters requesting Temporary Construction Easements sent to residents

 April 25, 2011

Town Council awards construction contract

 May 2, 2011

Construction starts

 July, 2011

Construction complete

 August 3, 2011 

Ribbon cutting ceremony held 

 November 18, 2011

Trees planted