Orchard Street NW Drainage Improvements

This proposed drainage improvement project will extend the curb and gutter from the edge of 445 Orchard Street to 441 Orchard Street NW.  Improvements include 150 linear feet of curb and gutter, sidewalk, drainage structures with associated earth work and tree removal. A new curb inlet will collect and convey runoff from the upstream drainage area and reduce ponding water on these properties during rain events. These drainage improvements will tie into the existing storm sewer system.


Project Details
Project design budget: $65,000
Project Manager: Christine Horner, PE
Anticipated construction date: Spring 2020

Orchard Street Drainage Improvements 100% Plan

Status Summary and Tentative Schedule
November 2018 Town Council awards design contract to Urban, LTD
January 2019 Survey work begins
April 2019 Initial concept plans received
June 26, 2019 Community Design Meeting to discuss concept plan
November 6, 2019 Community Design Meeting to discuss final design plan
April 27,  2020 Tentative Council approval of Construction Contract