Park Street NE Sidewalk
Park Street NE Sidewalk

This project will complete the sidewalk along the east side of Park Street NE between Ayr Hill Avenue NE and Albea Court NE

Project Details
Project design budget:  $500,000
Project manager:  Michael Gallagher PE
Anticipated construction date:  Summer 2019

Status Summary and Tentative Schedule
October 3, 2016 Town Council authorizes VDOT Revenue Sharing Grant Application
May 7, 2018 Town Council approves design contract
July 2018 Surveying begins
September 13, 2018 30% Design Plans Received