Ninovan Road SE Improvements
This project entails drainage improvements along the Ninovan Road SE right of way and the installation of new curb and gutter, relocation of utilities, and pavement replacement near the intersection of Ninovan Road SE and Talahi Road SE.

Project Details
Project budget:  $124,000
Project Manager: Luis Blandon
Anticipated construction date: Fall 2018

Talahi and Ninovan Roads SE Final Design Construction Plan


Status Summary and Tentative Schedule
August 2016 Town Council awards design contract to Urban, LTD
March 2018 Right of Entry Agreements mailed
March 2018 Final plans received
May 2018 Bid opening
August 2018 Town Council awards construction project
September 2018 Pre-construction meeting with contractor
October 29, 2018 Construction start