Piney Branch Stream Restoration
This project recreates a approximately 1,155 linear feet of natural stream and stabilizes the steep, eroded stream banks along Piney Branch at 600 Mill Street NE.  The completed project will reduce sedimentation and improve water quality of the stream using natural channel design techniques.

Project Details
Project design budget: $1,320,000
Project Manager: Christine Horner, P. E.
Anticipated construction date: TBD

Piney Branch 100% Plan - Addendum 1
Piney Branch Location Map
Piney Branch SLAF Grant

Status Summary and Tentative Schedule
February 17, 2017 Stream Restoration Grant Application submitted to Virginia Department of Environmental Quality (DEQ)
May 8, 2017 DEQ approved Stormwater Local Assistance Fund (SLAF) Grant
August 30, 2017 Design proposals received
October 16, 2017 Council approval of Fairfax County Funding Agreement
December 11, 2017 Council approval of Design Contract
January 29, 2018 Field survey and preliminary engineering begin
January 3, 2019 Citizen Meeting to present and discuss concept plans.
July 15, 2019 Citizen Meeting to present and discuss the 90% design plan before finalizing
October 15, 2019 100% Construction Document Received
November 26, 2019 Solicitation for Construction Bids Issued
December 19, 2019 Construction Bid due date
February 24, 2020 Tentative Council approval of Construction Contract