Maple Avenue E/W Repaving
This project includes milling and repaving Maple Avenue E & W (Section 1: between the town line at James Madison Drive and Lawyers Road NW; Section 2 between Lawyers Road NW and Beulah Road NE)  plus replacing settled curb, gutter, and sidewalk. Maple Avenue in Vienna is designated State Route 123 and is part of the National Highway System, therefore VDOT has approved a maintenance grant to fund the project.

Project Details
Project Budget: $1,175,000
Construction Manager:  Luis Blandon
Anticipated Construction Date:  Spring 2017

Maple Avenue Repaving limits of paving maps

March 18, 2016 Grant Application
August 5, 2016 VDOT approved Maintenance Grant
April 13, 2017 Town Council awards construction project
May 22, 2017 Construction Begins
August 18, 2017 Construction Complete