Ninovan and Talahi Drainage Improvements
This project entails curb, gutter, and storm drainage improvements on Ninovan and Talahi roads SE.

Project Details
Project budget:  $200,000
Project Manager: Christine Horner, P. E.
Anticipated construction date: Spring 2017

Talahi and Ninovan Roads SE Final Design Construction Plan


Status Summary and Tentative Schedule
November 18, 2016 Citizen Design Meeting
July 1, 2016 Survey Begins
October 17, 2016 Receive 35% Design Construction Drawings
October 19, 2016 Citizen Design Meeting
February 3, 2017 Receive 95% Design Construction Drawings
June 29, 2017 Receive 100% Design Construction Drawings
September 28, 2017 Citizen Design Meeting
February 12, 2018 Receive Revised 100% Design Construction Drawing
May 10, 2018 Construction Invitation for Bid Issued
May 30, 2018 Construction Bids Received