Maple Avenue E Repaving - East to Follin

This project includes milling and repaving Maple Avenue E plus replacing settled curb, gutter, and sidewalk. Maple Avenue in Vienna is designated State Route 123 and is part of the National Highway System, therefore VDOT has approved a maintenance grant to fund the project.

Project Details
Project Budget: $300,000
Construction Manager:  Luis Blandon
Anticipated Construction Date:  Summer 2016

February 3, 2015 Grant Application
June 18, 2015 VDOT approved Maintenance Grant
July 24, 2015 VDOT approved extension to Beulah Road
September 28, 2015  Bid advertised
October 22, 2015  Bid opening 
December 14, 2015  Construction contract award
March 22, 2016  Preconstruction meeting 
April 4, 2016  Construction start
April 23, 2016 Construction complete