Wolftrap Creek Stream Restoration Phase II
This project continues a previous one to recreate a natural stream and stabilize the steep, eroded stream banks along Wolftrap Creek from Follin Lane SE upstream to the Town boundary, approximately 1,020 linear feet. The completed project will reduce sedimentation and improve water quality of the stream.

Project Details

Project budget: $890,000
Project Manager: Christine Horner, PE
Anticipated construction date: Fall 2016

Wolftrap Creek location map

Wolftrap Creek Stream Restoration Final Design Plan

Wolftrap Creek Stream Restoration Bid File (.dwg)

Status Summary and Tentative Schedule
October 23, 2014 Stream restoration grant application
December 17, 2014 Grant approved
February 18, 2015 Design proposals received           
April 27, 2015  Council approval of Fairfax County Agreement and design contract
June 22, 2015 Field survey and preliminary engineering begin
October 28, 2015  Field inspection of preliminary layout 
February 11, 2016 Conceptual plan received
February 17, 2016 Citizen design concept meeting
June 13, 2017 Field Inspection of 95% draft plans
June 28, 2016 95% final plans received
July 6, 2016 Citizen design meeting
July 20, 2016 Final plan received
August 8, 2016 Submittal for VPDES Construction General Permit coverage to VA DEQ
August 31, 2016 Pre-construction notification submittal to U.S. Army Corps of Engineers
October 2016 Bid Package Under Review
December 8, 2016 Construction Project Advertised
December 21, 2016 Bid Opening
December 23, 2016 Received verification of coverage under Corps Nationwide Permit 27
January 12, 2017 Bid Due Date
March 2017 Final Plans Received
May 2017 Under Construction
February 27, 2017 Council Approval of Construction Contract
April 18, 2017 Pre Construction meeting with contractor
May 2017 Construction Begins
October 18, 2017 Major Construction Complete
February 22, 2018 Final plantings to be installed
February 2018 Project complete