2015 Water Main Replacement
Water mains in Vienna are a generally either cast iron or more modern ductal iron pipe. Pipe material, age, installation methods, soil types, and other factors affect the total life of individual pipes. More than three water main breaks have occurred at the following locations and the water mains identified for replacement:
  • Victoria Court NW (from Woodland Court to end) - July status, complete pending pavement restoration
  • Malcolm Road NW (from West Street and Lawyers Road) - July status, minor tie-in then pavement restoration
  • Glyndon Street SE (from Manvel Road to Moore Avenue) - July status, complete pending pavement restoration
  • Stephen Circle SE (from Meadow Lane to end) - July status, complete pending pavement restoration
  • Arcadian Circle SW (from Cottage Street to end) - July status, complete pending pavement restoration
  • Harmony Drive and Circle Drive SE (from Park Street to Lullaby Lane) - July status, complete pending pavement restoration
  • Courthouse Road SW (from Maple Avenue to Cherry Street SW) - deleted


Water Main Replacement Location Maps

Project Budget:  $1,046,621
Project Manager: David Donahue
Anticipated Construction Date:  Spring 2015
February 2, 2015 Town Council Construction Contract Award
March 9, 2015  Construction start