This project will replace existing asphalt trail with a concrete sidewalk and enclose the open roadway ditch on the northwest side of Old Courthouse Road NE from Gosnell Road to Pine Valley Drive.

Project Details
Project Budget:  $1,200,000
Project Manager:  Michael Gallagher, P.E.
Anticipated Construction Date:  To be determined

Old Courthouse Road NE Plans Phase 1

Old Courthouse Road NE Plans Phase 2


Status Summary and Tentative Schedule
October 28, 2013 Town Council authorized applying for Safe Routes to School sidewalk grant
November 6, 2013 Grant approved by VDOT for improvements at #401 and 405 only
December 12, 2013 Project administration agreement received
March 16, 2015  Town Council award of survey & design contract
July 6, 2015  Council approval of Fairfax County Agreement to expand project
July 6, 2015  Council award of design contract for expanded project
December 9, 2015  Design concept review with Fairfax County staff.
November 15, 2017 VDOT & Fairfax County Approval
December 22, 2017 Request VDOT Prepare Construction Agreement