Center and Battle Streets Storm Sewer Repair
This project entails completion of a missing section of storm sewer to collect groundwater runoff at Center Street and Battle Street S.

Project Details
Project design budget: To be determined
Project Manager:  Christine Horner, PE

Status Summary and Tentative Schedule
January 2015 Design contract to be awarded to Urban, LTD
March 25, 2015  Preliminary plan received
March 2016 Design complete