Hunters Branch Stream Restoration
This project stabilizes the steep eroded stream banks in Hunters Branch from Vienna Dog Park on Courthouse Road SW downstream to Tapawingo Road SW. The completed project will reduce sedimentation and improve water quality of the stream.

Project Details

Project budget: $1,340,000
Project Manager: Michael Gallagher P.E.
Anticipated construction date: Fall 2015 /Winter 2016

Hunters Branch Stream Restoration Location Map

Phase IA Archeological Investigation


Hunters Branch Pre-Design Presentation

CAD - Grading Plan

Final Design Plan

Status Summary and Tentative Schedule
October 28, 2013 Council approves cooperative water quality agreement with Fairfax County
November 15, 2013 Stream restoration grant application
December 19, 2013  Grant approved
May 15, 2014 Design proposals received           
August 18, 2014 Council approval of Fairfax County Agreement and design contract
December 9, 2014  Citizen design concept meeting
February 20, 2015 Concept plans received
March 18, 2015 Citizen meeting
September 17, 2015  Construction project advertised
October 13, 2015  Bid opening
November 16, 2015 Construction contract award by Council
December 8, 2015  Contractor Pre-Construction meeting
February 8, 2016 Construction begins
July 6, 2016 Major construction complete
October 2016 Final plantings to be installed
October 2016 Project complete