Sanitary Sewer Relining
This project involves inserting a rosin impregnated fabric inside the sewer pipe, then steam heating and expanding until cured.  The cured liner has a projected life of 50 to 100 years.

Lining is projected for:   
  •     Church Street NE between Council Drive and East Street NE  
  •     Lewis Street NW at West Street NW
  •     Maple Avenue West between Lawyers Road and Pleasant Street SW
  •     Maple Avenue West between Nutley Street SW and Glengyle Drive
  •     Moorefield townhomes between buildings
  •     Parking Lot of Vienna Shopping Center
  •     Plum Street SW between Cottage Street and Birch Street SW
  •     Roland Street SW between Wade Hampton Drive and Ceret Court SW
  •     Spring Street SE between Battle Street and Moore Avenue SE
  •     Walker Street SW (behind the homes) between Cottage Street SW and Southside Park

Project Details
Project budget: $310,000
Project Manager: Seth Haffner
Anticipated construction date: January 2014

Status Summary and Tentative Schedule
November 18, 2013 Town Council construction contract approval
January 6, 2014 Contractor televising sewer mains
March 4, 2014  Relining begins 
March 17, 2014  Town Council approves separate contract to grout Vienna Shopping Center sewer
April 25, 2014  Complete