Ninovan Road SE Sidewalk
This project constructs curb, gutter and sidewalk at 836 Ninovan Road SE.

Project Details
Project design budget: $36,000
Project Manager: Luis Blandon, PE
Anticipated construction date: Fall 2013

Status Summary and Tentative Schedule
November 13, 2013 Bid Opening
January 15, 2014  Construction Start