John Marshall Drive NW sidewalk
This sidewalk project will provide a safe pedestrian route from neighborhoods in the northwest section of Vienna to restaurants and other businesses in Vienna's commercial corridor. Completing a sidewalk on John Marshall Drive NW between Lawyers Road and Center Street N is #34 on the Sidewalk Task Force List.

Project Details
Project design budget: $33,500
Project Manager: Michael Gallagher, PE
Construction Manager:  Luis Blandon
Anticipated Construction Date: Fall 2015

Design Options

Concept A Color   Concept A Black & White

Concept B Color   Concept B Black & White

Concept C Color   Concept C Black & White

Final Design Concept Sidewalk on the South Side

Construction Plan

Status Summary and Tentative Schedule
September 17, 2012 Town Council authorizes VDOT Revenue Sharing Grant Application
September 10, 2013  Citizen notice letter, Council consideration of design contract 
September 23, 2013 Design Contract Awarded to Rinker Design Assoc.
May 1, 2014  3 Design Options letter to property owners
November 5, 2014  Final design concept letter to property owners 
November 17, 2014  7 P.M. design review meeting in upper lobby conference room 
April 27, 2014  Town Council increase design contract to include Holmes Drive intersection narrowing
May 15, 2015  Right-of-Entry request letters to all property owners
August 13, 2015  Construction bid advertised
August 27, 2015  Bid opening
September 14, 2015  Town Council award of construction contract
October 19, 2015  Construction start 
December 30, 2015  Complete pending striping and landscaping 
April 4, 2016  Complete