Glyndon Street NE Sidewalk
This project entails completion of missing sections of curb, gutter, and sidewalk on the west side of Glyndon Street and will connect to the recently completed sidewalk at Hilltop Road.

Project Details
Project design budget: $58,000
Project Manager:  Dennis Johnson
Construction Manager: Luis Blandon
Anticipated construction date: 2015

Glyndon Street NE Sidewalk 100% Plan

Status Summary and Tentative Schedule
September 23, 2013 Design Contract Awarded to Urban Engineering Assoc.
December 2013 60% design submitted
April 2014 100% design completed
May 2014  Acquiring Rights of Entry
May 29, 2014  Construction contract advertised
June 12, 2014  Bid Opening
August 18, 2014  Construction contract award
October 15, 2014 Waiting for gas company to relocate main
August 10, 2015  Gas company relocation underway
September 14, 2015  Construction started 
November 6, 2015  Complete pending landscape installations
November 13, 2015  Complete