Echols Street SE Reconstruction
This project entails rehabilitation of roadway,curb, gutter and sidewalk along Echols Street SE between Branch Road and Delano Drive to include the intersection with Delano Drive SE.

Project Details

Project Budget: $236,078
Project Manager: Luis Blandon
Anticipated construction date: 2014

Echols Street SE Reconstruction Standard Detail

Echols Street SE Detour Map

Status Summary and Tentative Schedule
October 2013  Bid Package Being Prepared
October 30, 2013 Bid Opening
December 12, 2013 Council resolution to reclassify project funding
February 24, 2014 Town Council award of construction contract
May 27, 2014  Construction start
July 3, 2014 (after 3:30 p.m.) Construction complete