The project involves installing a new stationary diesel generator sized to meet the needs of the existing building and a future expansion, within a new enclosure.  The existing natural gas generator will be moved and installed at Town Hall.

Project Details

Project Budget: $411,000
Project Manager: Dennis Johnson, P.E.
Anticipated construction date: Spring 2014

Status Summary and Tentative Schedule
September 17, 2012 Town Council awarded design contract to Wiley|Wilson
August 27, 2013  Bid Opening
September 23, 2013 Contract Awarded to Elite Power & Energy Corporation
January 2, 2014 Electrical permit plans submitted
February 20, 2014  Board of Zoning Appeal consideration of variance
May 12, 2014  Construction start
August 4, 2014  Requested Dominion Power cut-over to new generator