This project replaces the culvert under Nutley Street SW between Kingsley and Marshall roads SW.

Project Details
Project budget: $500,000
Project Manager: Michael Gallagher PE.
Anticipated construction date: To be determined

Nutley Street SW Culvert plans

Status Summary and Tentative Schedule
June 2012 Town Council approved contract for drainage study
March 21, 2013 On-site citizen meeting
November 18, 2013 Town Council award of final design contract 
July 10, 2014 60% Plans Received
November 20, 2014  On-site citizen meeting
May 8, 2015  Design review by VDOT
August 21, 2015  On-site citizen final plan review
March 7, 2016  Town Council to approve additional funds for additional hydraulic analysis
March 2017 Pending future CIP funding