Meadow Lane and Gibson Drive SW - Drainage Improvements
This project will improve the public drainage system at the intersection of Meadow Lane SW and Gibson Drive SW.

Project Details
Project budget: $200,000
Project Manager: Michael Gallagher P.E.
Anticipated construction date: 2014

Status Summary and Tentative Schedule
June 2012 Town Council approved funds for design contract
March 14, 2013 On site citizen meeting
November 7, 2013  Construction contract out for bid
December 4, 2013  Bid opening
January 27, 2014  Construction contract award 
March 17, 2014  Utility adjustmetns begin
May 27, 2014  Construction start 
October 17, 2014 Completion