Westbriar Drive NE - Walk to Downtown
This sidewalk project completes the missing section of sidewalk on Westbriar Drive NE between Maple Avenue E to Saint Bernard Drive NE. The Walk to Downtown Initiative completes sidewalks within the first block side streets along Maple Avenue, Vienna's commercial corridor, to provide safe routes for residents to walk to businesses, restaurants, and bus stops.

Project Details

Project Budget: 310,000
Project Manager: Dennis Johnson, P.E.
Construction Manager:  Luis Blandon
Anticipated construction date: 2015

Westbriar Drive SW Sidewalk Plan

Status Summary and Tentative Schedule
November 5, 2012 Town Council authorized Walk to Downtown Grant Application
January 14, 2013 Town Council award of survey and design contract
November 27, 2013 Acquiring easements
January 22, 2015  Preparing construction contract bid
March 18, 2015  Bid advertised
April 27, 2015  Construction contract award 
May 27, 2015  Preconstruction meeting
June 8, 2015  Construction start 
August 14, 2015  Complete pending landscaping
November 13, 2015  Complete