Wade Hampton Drive SW - Walk to Downtown
This sidewalk project completes the missing section of sidewalk on Wade Hampton Drive SW from Maple Avenue W to Glen Avenue SW / Millwood Court SW. The Walk to Downtown Initiative completes sidewalks within the first block of Maple Avenue, Vienna's commercial corridor, to provide safe routes for residents to walk to businesses, restaurants and bus stops.

Project Details

Project Budget: $100,000
Project Manager:  Dennis Johnson
Construction Manager: Luis Blandon
Anticipated construction date: Winter 2014/5

Wade Hampton Drive SW 100% plans

Status Summary and Tentative Schedule
November 5, 2012 Town Council authorized Walk to Downtown Grant Application
January 14, 2013 Town Council award of survey and design contract
December 23, 2013 Acquiring easements
March 17, 2014  Town Council acceptance of easements
July 1, 2014  Preparing construction contract bid 
September 18, 2014 Bid opening 
October 20, 2014 Construction contract award
December 3, 2014  Preconstruction meeting 
December 15, 2014  Projected start of construction
January 30, 2015  Complete