Northside Connector Trail

Project Description:This projects consists of the construction of approximately 125-foot boardwalk style trail and 50-foot asphalt trail. This section will connect the W& OD Trail and the Richard Black Bridge to the Northeast Vienna. The boardwalk will be elevated in sections and will be made of a composite wood.
Section of Town or address:Northside Park, can be reached from Mill Street, NE or Glyndon Street, NE
Project Manager:Cathy Salgado
Design Consultant:Whitman, Requardt and Associates
Design % Complete:100%
Project Budget:$125,000
Engineering Estimate:$17,700
Construction Manager:Cathy Salgado
Construction Firm:Bid awarded on 10/22/2007
Construction Start Date:November 2007
Original Completion Date:March 2008
Revised Completion Date:March 2008
Original Bid Amount:$79,764
Change Order Value to Date:$0, project completed on budget.
Design Comments:Project Completed by Webb Construction.
Construction Comments:Construction has been completed.
Updated:03/10/2008