Westbriar Ct., N.E., Storm Drainage Improvements
|
Project Description:
|
Installation of covered pipe to replace existing concrete drainage ditch.
|
|
Section of Town or address:
|
Westbriar Ct., N.E.
|
|
Project Manager:
|
Holly M. Chu, PE 703-255-6387
|
|
Design Consultant:
|
Whitman, Requardt & Assoc.
|
|
Design % Complete:
|
100%
|
|
Project Budget:
|
To be established by Town Council.
|
|
Engineering Construction Estimate:
|
$131,940.38
|
|
Construction Manager:
|
Unknown at this time
|
|
Construction Firm:
|
Sagres Construction Corp.
|
|
Construction Start Date:
|
Fall 2006
|
|
Original Completion Date:
|
|
|
Revised Completion Date:
|
|
|
Original Bid Amount:
|
|
|
Change Order Value to Date:
|
|
|
Design Comments:
|
|
|
Construction Comments:
|
Need recordation of easements and Council funding
|
|
Updated:
|
6/30/2006
|
|
|
|